A wider Farm House Lane

Concrete crew pours a section of Farm House Lane.

A team from Adair-based Caliber Concrete pours a section of the northbound lane for a new, wider Farm House Lane on June 28. Visible on the left side of the image is the Farm House Museum. The sidewalk along the east side of the lane remains open from Osborn Drive to Wallace Road. Photo by Christopher Gannon.

Last week, crews began pouring sections of concrete for a new Farm House Lane. The middle section of road is being replaced, from Troxel to Curtiss halls (access remains to parking lots adjacent to both buildings). Farm House Lane is being widened to 21 feet so oncoming vehicles can pass each other safely. The road and west sidewalk are scheduled for completion during the second week of August.

Bicycle parking zones along the lane are being replaced as part of the project. Due to delivery delays, temporary bike racks will be set until the new bike hoops arrive.